Enabling Full-Load Operation Under Grid Limits in the Netherlands

Project Overview

In response to rising electrification demand in the Netherlands, many industrial sites face contracted grid limits and legacy electrical infrastructure that cannot be upgraded quickly. This project demonstrates how a 100kW/215kWh BESS can provide capacity relief for an industrial facility in the Netherlands, bridging the gap between the utility-approved connection capacity and the site’s full-load operating demand. By allowing the PCS and the grid to supply the loads in parallel and prioritizing on-site PV for self-consumption and battery charging, the solution enables the factory to run all equipment while minimizing grid import and avoiding costly grid upgrades.

Project Background

In the Netherlands, many industrial sites face strict limits on contracted grid capacity. When production expands or more equipment is commissioned, the facility’s total load can exceed the utility-approved connection power. Upgrading the grid connection may require long lead times and additional costs. In this project, the customer also had on-site PV and wanted to maximize self-consumption while keeping grid import as low as possible.

Project Challenge

FFD POWER Solution

FFD POWER deployed a behind-the-meter BESS with PCS and EMS control to deliver capacity relief. During high-demand periods, the PCS discharges the battery to support the site loads while the grid continues to supply within the contracted limit. When on-site PV generation is available, PV is prioritized to supply the load; surplus PV charges the BESS under EMS power limits. This coordinated control allows full-load operation, reduces peak grid import, and defers or avoids a grid connection upgrade.

System Specifications

Operational Logic: Capacity Relief Behind the Meter

The EMS prioritizes self-consumption and enforces the site’s grid import constraints: